Stadium construction is underway at the full speed
09.08.2013
Deputy general director for stadium construction Vladimir Sudarikov told pfc-cska.com how the works at the site are progressing.
- — Construction resumed in the beginning of the year, and now works are underway at the full speed. Now earthworks are being completed for the Southern, Western and Eastern stands. Similar work for the Northern stand will begin after the utilities network relocation. The stadium project foresees a 142-meter high tower, that will look like UEFA Cup trophy. Now we are preparing the bed plate for it.
- As for the parking, their total capacity will be 1400 car-places. We will have a separate indoor parking place for 750 cars, 600 places will be in the underground area. A hotel will be located in the North-Eastern corner building. There will also be a restaurant at the stadium. And, of course, the Youth academy will be housed at our arena.
- President of the club set a task - the first home match must be played at the new stadium in the spring of 2015. We'll try to complete the job in time, and the contractors assures us that sports sector will be ready on schedule.
Share:
Твитнуть
Плюсануть
Поделиться
Отправить
Класснуть
Запинить